August 2025 Grupo ACA Construction team casted first span of 816m length river Lima bridge.
The Overhead movable scaffolding system of Strukturas created a perfect opportunity to reach maximum productivity – complete 25 spans in just 8 months.
Bridge construction is planning to by finished in March of 2026 as last spans and Overhead MSS will be demobilized.
This project is a true example of planning, coordination, and execution in large-scale infrastructure.
OHMSS Highlights and facts:
- Max Span: 33,0m
- Min Span: 22,45m
- Max MSS Span: 33,0m
- Weight of Superstructure: Approx 26.2t/m
- Width Of Bridge Slab: 15,9m
- Max Crossfall: N.A.
- Max Long Slope: 4,8%